Report Back to Projects
Ongoing Borehole, Water Supply Approved

Nairobi Arboretum

Nairobi · Dagoretti North · Kilimani

Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling and equipping, solarization and construction of elevated water tanks with Associated distribution networks.
Start Date
06 May 2020
Planned End
02 Mar 2021
Actual End
02 Mar 2021
Contractor
Export Hydro Pump and Services Limited
Consultant
-
Location Type
Urban
Target Areas
Kilimani
Scope of Works
Drilling and equipping of borehole,Borehole chamber and pump house,Water kiosk and Reticulation
GPS Coordinates
1.2785277,36.7985582
Funding Sources

No funding sources recorded.

Total KES 0.0M
Technical Specs
Storage Reservoir 24.00 m³
Created 16 Aug 2026, 17:18 · Last updated 16 Aug 2026, 17:18
County Overview
Loading…
Loading…

Fetching entity performance details…