Ongoing
Borehole, Water Supply
Approved
Shadrack Kimalel School - Kibera Laini saba
Nairobi · Kibra · Laini Saba
Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling and equipping, solarization and construction of elevated water tanks with Associated distribution networks.
Start Date
06 May 2020
Planned End
06 May 2021
Actual End
06 May 2021
Contractor
Export Hydro Pump and Services (Africa) Limited
Consultant
-
Location Type
Urban
Target Areas
Laini Saba
Scope of Works
Construction of an elevated tank 24m3 on 18m steel tower.
Remarks
Operational
GPS Coordinates
1.3107436,36.7961924
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.2M
Total
KES 3.2M
Beneficiaries
312
Households
1,560
Population
Technical Specs
Volume Abstracted
78.00 m³/day
Storage Reservoir
24.00 m³
Created 16 Aug 2026, 17:18