Ongoing
Borehole, Water Supply
Approved
Bangladesh- Rongai
Kajiado · Kajiado North · Nkaimurunya
Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling and equipping, solarization and construction of elevated water tanks with Associated distribution networks.
Start Date
-
Planned End
-
Actual End
-
Contractor
Bavko Engineering Kenya LTD
Consultant
-
Location Type
Urban
Target Areas
Nkaimurunya
Scope of Works
Drilling, Equipping, Power Connection, 1No. Water Kiosks & Associated Piping, Elevated Tank
Remarks
Operational
GPS Coordinates
1.3961434,36.7388132
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 8.0M
Total
KES 8.0M
Beneficiaries
560
Households
2,800
Population
Technical Specs
Volume Abstracted
140.00 m³/day
Storage Reservoir
24.00 m³
Water Kiosks
1