Ongoing
Borehole, Water Supply
Approved
Silanga PCEA
Nairobi · Lang'ata · Kibera
Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling and equipping, solarization and construction of elevated water tanks with Associated distribution networks.
Start Date
-
Planned End
-
Actual End
-
Contractor
Turn-O- Metal Engineers Ltd
Consultant
-
Location Type
Urban
Target Areas
Kibera
Scope of Works
Drilling and equipping of borehole,Borehole chamber and pump house,Power Connection, 3No. Water Kiosk & Associated Piping and 1No. Elevated Tank
Key Challenges
Faulty motor and pump. Requires replacement.
Remarks
Not Operational
GPS Coordinates
1.3161541,36.7933825
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 0.3M
Total
KES 0.3M
Beneficiaries
360
Households
1,800
Population
Technical Specs
Volume Abstracted
328.00 m³/day
Storage Reservoir
24.00 m³
Water Kiosks
3
Created 16 Aug 2026, 17:18