Report Back to Projects
Ongoing Borehole, Water Supply Approved

Kagaa Chiefs Camp

Murang'a · Kigumo · Wangu

Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling and equipping, solarization and construction of elevated water tanks with Associated distribution networks.
Start Date
-
Planned End
-
Actual End
-
Contractor
Turn-O- Metal Engineers Ltd
Consultant
-
Location Type
Rural
Target Areas
Wangu
Scope of Works
Construction of an Elevated Tank 24m3 on 18m steel tower & Associated Piping.
GPS Coordinates
1.2070865,36.6965889
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 0.1M
Total KES 0.1M
Beneficiaries
119
Households
3,999
Population
Technical Specs
Storage Reservoir 24.00 m³
Created 16 Aug 2026, 17:19
County Overview
Loading…
Loading…