Ongoing
Borehole, Water Supply
Approved
Kagaa Chiefs Camp
Murang'a · Kigumo · Wangu
Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling and equipping, solarization and construction of elevated water tanks with Associated distribution networks.
Start Date
-
Planned End
-
Actual End
-
Contractor
Turn-O- Metal Engineers Ltd
Consultant
-
Location Type
Rural
Target Areas
Wangu
Scope of Works
Construction of an Elevated Tank 24m3 on 18m steel tower & Associated Piping.
GPS Coordinates
1.2070865,36.6965889
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 0.1M
Total
KES 0.1M
Beneficiaries
119
Households
3,999
Population
Technical Specs
Storage Reservoir
24.00 m³