Ongoing
Borehole
Approved
Kapkoto Primary School Water Project
Bungoma · Mt. Elgon · Chesikaki
Overall Progress
95.00%
Project Overview
Implementing Agency
Lake Victoria North Water Works Development Agency
Programme
National Water Harvesting and Groundwater Exploitation
Start Date
-
Planned End
-
Actual End
-
Contractor
Tois investment
Consultant
l
Location Type
Rural
Target Areas
Kapkoto
Scope of Works
installation of solar power hybrid system, solar floodlight and a submersible pump
supply and installation of 18m3 elevated structurally pressed steel tank on 8m tower
rising main from the borehole to the elevated steel tank (25m length) 50mm dia
distribution line to secondary school
distribution line to primary school
distribution line to kapkoto dispensary
communal water points
Impacts
Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
Key Challenges
Insufficient budget allocation and late disbursement of project funds which led to delays and limitations in scope.
Remarks
Project is almost complete
GPS Coordinates
Latitude 0.7369156
Longitude 34.89767164
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 8.0M
Total
KES 8.0M
Beneficiaries
300
Households
1,200
Population
Technical Specs
Volume Abstracted
50.40 m³/day
Treatment Capacity
40.32 m³/day
Storage Reservoir
18.00 m³
Treated Water Mains
0.03 km
Distribution Lines
600.00 km
Water Kiosks
5
Connections
10