Proposed
Water Supply
Approved
Sarora Springs-Kurgung-,koisolik, Fr. Lelei & Rubet Schools and Kapkoros Community Cluster Water Project.
Nandi · Mosop · Kapanga
Overall Progress
0.00%
Project Overview
Implementing Agency
Lake Victoria North Water Works Development Agency
Programme
GOK Funded Projects
Start Date
05 Feb 2025
Planned End
05 Aug 2025
Actual End
-
Contractor
Crossland construction and General supplies ltd
Consultant
No
Location Type
Rural
Target Areas
Sarora Springs, Kurgung, koisolik, Fr. Lelei ,Rubet , Kapkoros
Scope of Works
Spring protection
Installation of submersible pump and solar hybrid system
Rising main to kapkoros tanks hdpe (2300m length) od90mm dia
Main and distribution lines (8,500m length) hdpe od 90mm-40mm dia
Construction of 4no. 30m3 steel tank
Renovation of existing pump house and masonry tanks
Construction of 15 no. communal water points
Construction of 3no. standard water kiosk
Impacts
Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
Key Challenges
Late disbursement of funds
Remarks
project yet to start
GPS Coordinates
Latitude : 0.4177238666
Longitude: 35.017635115
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 28.0M
Total
KES 28.0M
Beneficiaries
2,344
Households
9,375
Population
Technical Specs
Volume Abstracted
300.00 m³/day
Treatment Capacity
300.00 m³/day
Storage Reservoir
420.00 m³
Treated Water Mains
2.30 km
Distribution Lines
8.50 km
Water Kiosks
18
Connections
20