Ongoing
Water Supply
Approved
Wabukhonyi water project
Bungoma · Tongaren · Ndivisi
Overall Progress
20.00%
Project Overview
Implementing Agency
Lake Victoria North Water Works Development Agency
Programme
GOK Funded Projects
Start Date
06 Mar 2024
Planned End
06 Sep 2024
Actual End
-
Contractor
Hampton Construction Company Limited
Consultant
-
Location Type
Rural
Target Areas
Wabukhonyi
Scope of Works
1. Solar and pump at Wabukhonyi and Muungano Water Project
2. Rehabilitation works for the elevated steel tank
3. Laying of 7000m long HDPE Pipeline
4. Rehabilitation of 4nr. Water Kiosks
Impacts
Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
Key Challenges
Insufficient budget allocation which led to delays and limitations in scope and late disbursement of funds
Remarks
Slow progress
GPS Coordinates
Latitude 0.7505924
Longitude 34.785609
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 10.0M
Total
KES 10.0M
Beneficiaries
500
Households
2,500
Population
Technical Specs
Volume Abstracted
160.00 m³/day
Treatment Capacity
160.00 m³/day
Storage Reservoir
100.00 m³
Treated Water Mains
0.35 km
Distribution Lines
7.00 km
Water Kiosks
4
Connections
20