Ongoing
Borehole
Approved
Water storage facility at Kapkatenyi Pri. Sch
Bungoma · Mt. Elgon · Kapkateny
Overall Progress
40.00%
Project Overview
Implementing Agency
Lake Victoria North Water Works Development Agency
Programme
GOK Funded Projects
Start Date
11 Apr 2024
Planned End
11 Oct 2024
Actual End
-
Contractor
Raslan Investment Limited
Consultant
-
Location Type
Rural
Target Areas
Kapkateny
Scope of Works
Gravity line to masonry tank 300m length (100mm DIA), 100m3 masonry tank, Ndarut distribution line 1600m length (100mm - 32mm DIA), Chebin distribution lines 1700m length, Sacha distribution line 1400m length and Communal water point
Impacts
Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
Key Challenges
Insufficient budget allocation which led to delays and limitations in scope and late disbursement of funds
Remarks
Slow progress
GPS Coordinates
Latitude 0.801147043
Longitude 34.6224207
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 10.0M
Total
KES 10.0M
Beneficiaries
122
Households
1,600
Population
Created 16 Aug 2026, 17:19