Ongoing
Unknown
Approved
Siaya Bondo Sewer Project
Siaya · Bondo · Nyawita and Barkowino
Overall Progress
1.00%
Project Overview
Implementing Agency
Lake Victoria South Water Works Development Agency
Programme
SMALL TOWNS RURAL WATER SUPPLY AND SANITATION PROJECT
Start Date
-
Planned End
-
Actual End
-
Contractor
Jiangxi Hydropower Limited.
Consultant
Wapcos Ltd
Location Type
Rural Urban
Target Areas
Bondo Town
Scope of Works
• Inlet Chamber including coarse and fine screen chambers
• Sullage channel with parshall flume
• Distribution chamber
• 2 No. Anaerobic ponds
• 1 No. Facultative pond
• 2 No. Maturation ponds
.
• 15.1 km precast concrete sewer lines of diameters 300mm to 225mm in Bondo town.
• 4 No. public ablution blocks.
Impacts
Improved health and socioeconomic
wellbeing of the
population
Key Challenges
Delayed payment to contractor due to delayed exchequer releases
Remarks
Project Complete and operational
GPS Coordinates
0°04'23.4"N 34°15'03.6"E
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 216.4M
Adb
🌍 Foreign
· Loan
KES 24.0M
Total
KES 240.4M
Beneficiaries
6,600
Households
33,000
Population
Technical Specs
Connections
130
Wastewater Production Capacity
4,515.00 m³/day
Wastewater Treatment Capacity
4,515.00 m³/day
Trunk Sewer Main
15.10 km
Reticulation Sewer
5.00 km
Manholes
160
Non-Sewered Sanitation Facilities
4
Sewer Connections (Households)
130
Created 16 Aug 2026, 17:19