Report Back to Projects
Ongoing Pipeline Rehabilitation & Extensions Approved

LOT 1/Improvement of storm water outlets and combined sewer overflows in Mombasa Island

- · - · -

Overall Progress
68.00%
Project Overview
Implementing Agency
State Department for Water and Sanitation
Programme
Water & Sanitation Development Project (WSDP)
Start Date
05 Nov 2021
Planned End
-
Actual End
-
Contractor
Adequate Machinery Construction Company Ltd
Consultant
Batch Associates Ltd JV Tertiary Consulting Engineers Ltd
Location Type
-
Scope of Works
Rehabilitation/Modification Pumping station and water Outlets, Inlet Works, Screening Channel, Grit Removal screens, Outlet Pipe to low-low tide water level, Washroom Facilities and Store/Guard Houses.
Funding Sources
Wb
🌍 Foreign · Loan
KES 459.1M
Total KES 459.1M
Beneficiaries
875
Households
300,000
Population
Created 16 Aug 2026, 17:19 · Last updated 16 Aug 2026, 17:19
County Overview
Loading…
Loading…

Fetching entity performance details…