Design and Construction of Mwache Water Treatment Plant, Transmission Mains, Terminal Reservoirs, Distribution and Sanitation Works
- · - · -
Overall Progress
0.00%
Project Overview
Implementing Agency
Coast Water Works Development Agency
Programme
Improvement of drinking water in mombasa
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Rural Urban
Scope of Works
186,000 m3 Treatment plant, 65 km ranging between 700-1200 mm epoxy coated steel pipes, 4 terminal reseviors, Distribution Networks and Sanitation Systems.
Remarks
Detailed designs ready/ Procurement of contractor ongoing.
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
8,000
Households
40,000
Population
Technical Specs
Volume Abstracted
186,000.00 m³/day
Treatment Capacity
186,000.00 m³/day
Storage Reservoir
98,000.00 m³
Treated Water Mains
58.00 km