Proposed
Unknown
Approved
Construction of Mbulia water Project
- · - · -
Overall Progress
0.00%
Project Overview
Implementing Agency
Coast Water Works Development Agency
Programme
GOK Funded Projects
Start Date
01 Apr 2021
Planned End
-
Actual End
10 Apr 2022
Contractor
Kiburu Enterprises Ltd
Consultant
-
Location Type
-
Scope of Works
Pipeline Construction
Construction of 3 No. standard water kiosks
Impacts
Project Completed. 250 Households connected
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
250
Households
1,250
Population
Created 16 Aug 2026, 17:19