Drilling and Equipping of Ikuminyi Borehole

Taita-Taveta · Wundanyi · Werugha

Overall Progress
20.00%
Project Overview
Implementing Agency
Coast Water Works Development Agency
Programme
GOK Funded Projects
Start Date
01 Oct 2025
Planned End
07 Sep 2025
Actual End
07 Sep 2025
Contractor
Ryland Coast Investments Limited
Consultant
None
Location Type
Rural
Target Areas
Ikuminyi village
Scope of Works
Drilling of a borehole,Equipping with solar, 10cm³ storage tank on an elevated platform and associated works
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 10.0M
Total KES 10.0M
Beneficiaries
200
Households
1,000
Population
Technical Specs
Storage Reservoir 10.00 m³
Distribution Lines 0.30 km
Water Kiosks 2
Created 16 Aug 2026, 17:19