Report Back to Projects
Ongoing Fecal Sludge Treatment Plant (FSTP) Approved

Construction of 1No. 93m3/day Waste to Value Feacal Sludge Treatment Plant in Malindi Town

- · - · -

Overall Progress
36.70%
Project Overview
Implementing Agency
State Department for Water and Sanitation
Programme
Water & Sanitation Development Project (WSDP)
Start Date
10 Dec 2021
Planned End
-
Actual End
-
Contractor
Abgale General Contractors
Consultant
Design Master Plan in JV with Studio Galli Ingegnera (SGI)
Location Type
Urban
Scope of Works
Construction of a 93m3/day capacity waste to value sludge treatment plant in Malindi town-Sabaki area
Impacts
>Protection of public health >Environmental preservation >Water reclamation(for irrigation) >Economic benefits for the operator and the community from employment at the facility and selling briquettes as well as benefits to the WSP from the rent, water bill payments and a percentage of the profit from selling the briquettes >Healthy and sustainable community due to improved quality of life
Key Challenges
>Delay in site handover due to PAP resettlement >Cash flow challenges due to extended disbursement procedures >Delay in making pertinent decisions (Electromechanical works procurement)
Remarks
Improvement of waste handling in Malindi town. Implemented by MAWASCO under WSDP
Funding Sources
Wb
🌍 Foreign · Loan
KES 587.5M
Total KES 587.5M
Beneficiaries
2,500
Households
12,500
Population
Technical Specs
Wastewater Production Capacity 93.00 m³/day
Created 16 Aug 2026, 17:19