Ongoing
Pipeline Construction
Approved
Upgrade of water distribution systems for Voi, Taveta, Mwatate and Wundanyi towns
- · - · -
Overall Progress
68.20%
Project Overview
Implementing Agency
State Department for Water and Sanitation
Programme
Water & Sanitation Development Project (WSDP)
Start Date
-
Planned End
-
Actual End
-
Contractor
Suhufi Agencies Ltd
Consultant
Runji Consulting Group Ltd
Location Type
-
Target Areas
Voi, Taveta, Mwatate and Wundanyi towns
Scope of Works
Installation of Primary Lines, tertiary service mains & Consumer Connections and Supply of Bulk Meters forVoi, Wundanyi, Taveta & Mwatate
GPS Coordinates
38.370049, -3.508413
Funding Sources
Wb
🌍 Foreign
· Loan
KES 214.9M
Total
KES 214.9M
Beneficiaries
3,500
Households
17,500
Population
Technical Specs
Treated Water Mains
43.21 km
Distribution Lines
54.80 km
Connections
3,500
Created 16 Aug 2026, 17:19
· Last updated 16 Aug 2026, 17:19