Report Back to Projects
Ongoing Boreholes Approved

Rehabilitation and Construction of Boreholes (Group 3)

- · - · -

Overall Progress
45.00%
Project Overview
Implementing Agency
State Department for Water and Sanitation
Programme
Water & Sanitation Development Project (WSDP)
Start Date
04 Sep 2021
Planned End
01 Jan 2025
Actual End
-
Contractor
Africa Water Drilling Ltd
Consultant
Runji Consulting Group Ltd
Location Type
-
Scope of Works
Drilling & Equipping 7 boreholes, Supply and installation of Solar PV Power Supply, Supply and installation of 100m3 elevated pressed steel collection tank on a 10m steel tower, Construction of community water kiosks Construction livestock watering troughs, Construction of well-ventilated Control/Generator house, Fencing borehole sites
Funding Sources
Wb
🌍 Foreign · Loan
KES 75.8M
Total KES 75.8M
Beneficiaries
1,770
Households
17,700
Population
Technical Specs
Volume Abstracted 496.00 m³/day
Created 16 Aug 2026, 17:19
County Overview
Loading…
Loading…