Report Back to Projects
Ongoing Borehole

Chorwet Primary School

Kwale · Kinango · Kinango

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Contractor
Chara Holding Limited
Consultant
Start Date
06 Apr 2024
Planned End
17 May 2024
Actual End
17 May 2024
Scope of Works
Drilling and Capping
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
450
Households
2,300
Population