Ongoing
Borehole
Baraka Nursery
Kwale · Kinango · Mackinon Road
Overall Progress
90.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Contractor
Muluna Enterprises Limited
Consultant
—
Start Date
18 Mar 2024
Planned End
16 Jun 2024
Actual End
20 Aug 2026
Scope of Works
Drilling, Equipping and Civil Works
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
500
Households
4,500
Population