Ongoing
Borehole
Karandi community borehole
Kwale · Kinango · Mwavumbo
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Contractor
Yellowstone Engineering Limited
Consultant
—
Start Date
08 Aug 2024
Planned End
13 Oct 2024
Actual End
13 Oct 2024
Scope of Works
Drilling and capping
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
500
Households
2,500
Population