Report Back to Projects
Ongoing Borehole

Thigio Primary School Bh

Kwale · Lunga Lunga · Dzombo

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Contractor
Finch Logistics limited
Consultant
Start Date
19 Sep 2026
Planned End
20 Dec 2026
Actual End
30 Oct 2024
Scope of Works
Equipping and Civil works
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
500
Households
2,500
Population