Report Back to Projects
Ongoing Borehole

Chemasis community borehole

Mombasa · Nyali · Ziwani/Kadzandani

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Contractor
Maroc East Africa Limited
Consultant
Start Date
07 Aug 2024
Planned End
07 Sep 2026
Actual End
29 Aug 2024
Scope of Works
Drilling and capping
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
230
Households
2,100
Population