Report Back to Projects
Ongoing Wier

Chumet Water Supply

Kilifi · Kilifi South · Chasimba

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects
Contractor
Eltons technology and systems limuted
Consultant
Start Date
Planned End
Actual End
02 Nov 2025
Scope of Works
Construction of (Intake works,gravity main pipeline,cattle trough and communal water point)
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
500
Households
2,500
Population