Ongoing
Water Supply River intake
Rehabilitation of Mugitiri water project
Kwale · Matuga · Tiwi
Overall Progress
30.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Projects From For Fy 2022/23
Contractor
—
Consultant
—
Start Date
22 Apr 2022
Planned End
01 Aug 2022
Actual End
01 Aug 2022
Scope of Works
Construction of Intake weir. Gravity main and Rehabilitation of Existing network
Impacts
Improved access to water supply
Key Challenges
Slow contractor mobilization
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
400
Households
2,000
Population