Ongoing
Water Supply
Construction of Kaptumo water project phase 4 (Kaptumo-Sogon Water Supply)
Kilifi · Magarini · Maarafa
Overall Progress
80.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Projects From For Fy 2022/23
Contractor
—
Consultant
—
Start Date
10 Feb 2023
Planned End
04 Feb 2024
Actual End
04 Feb 2024
Scope of Works
1. Extension of pipeline from Chepkabomo Masonry sump to Sogon Tank | 2. Construction of 1No Water Kiosk | 3. Construction of Student Water point | 4. Solarization of Kasau Reservoir pumping system | 5. Solarization of Talai Borehole | 6. Construction of Pit Latrines for Sogon and Kaptumo Primary Schools | 7. Construction of Wash basins for Sogon and Talai Primary Schools | 8. Construction of 4m high steel tower with 10,000 lts plastic tank for | Talai Primary School and Sogon Dispensary.
Impacts
Improved access to water supply
Key Challenges
Slow contractor mobilization
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
400
Households
2,000
Population