Ongoing Borehole

Drilling and capping of Muchukwo community Borehole

Kilifi · Magarini · Gongoni

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Water Harvesting Programme 2024/25
Contractor
Consultant
Start Date
08 May 2024
Planned End
08 Jul 2024
Actual End
08 Jul 2024
Scope of Works
Drilling and capping.
Impacts
Improved access to water
Key Challenges
No challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
400
Households
2,000
Population