Central Rift Valley Water Works Development Agency
Program
Naivasha Industrial Park Water supply Project
Progress
100.00%
Location Information
County
Mombasa
Constituency
Changamwe
Ward
Kipevu
Setting
Urban
Coordinates
-1.048068, 36.334585
Timeline & Impact
Start Date
2020-02-24
Planned End Date
2021-08-01
Scope of Works
•Driling of 5no boreholes | • Pumping main from NAIVAWASCO Borehole Site (Near Delamere) to the Main Tank at Longonot . | • Pumping main-22km-400mm diameter and Gravity main 28km -300mm- diameter | • 4,500m3 Reinforced Concrete Tank longonot | • 500m3 Reinforced Concrete Tank -booster to longonot | • 100m3 Reinforced Concrete Break Pressure Tank -BPT | • 2 No. 262m3 Elevated Steel Tanks | • Pump and Pump Houses
Impacts
Improve access to water
Challenges
No challenges during construction. | | | Narok Water Service Provider has reported vandalism and theft of Galvanised steel pipes