| Start Date | 2022-07-12 |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Laghatogwein investment LTD |
| Consultant | None |
| Target Areas | Ifo refugee camps |
| Scope of Works | Drill & develop 1 borehole and fencing; 30 KW solar system installation; 1.3 Kms HDPE pipeline extension, 100m3 Elevated Steel tank, 4 No. 4 door VIP latrines, 10 Arce Horticulture Production |
| Impacts | The proposed works delayed due to natural(rains) and human causes (lack contractor commitment & insecurity) related complexities. |
| Challenges | 3 sections targeted by the new borehole in Ifo refugee camp, the water distribution systems are interconnected, therefore additional 409HH will be accessing water from the new borehole once the nearby boreholes breakdown) |
| Remarks | On-going project |