Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Borehole |
| Agency | Water Sector Trust Fund |
| Program | Sustainable Management and Access to Water and Sanitation in the ASALs |
| Progress | 40.00% |
| County | Garissa |
|---|---|
| Constituency | Ijara |
| Ward | Masalani ward, Abalatiro, Kotile, Korisa and Hara Villages |
| Setting | Rural |
| Coordinates | 1.981304, 40.180400 |
| Start Date | 2022-07-12 |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | M/s Laghatogwein Investment Ltd |
| Consultant | None |
| Target Areas | Kotile |
| Scope of Works | Drilling of 1 No. borehole and fencing, 18.5 KW solar pumping system installation, 16.1 Kms HDPE pipeline extension, 1 No. 50m3 elevated Steel tanks, Rehabilitation of 8 No. Water Kiosks, 7 No. 4 door VIP latrines, CLTS in 30 villages, Excavation of a 40,000m3 Water Pan, 100 No. Energy saving Jikos |
| Impacts | increased access to water and sanitation services in ASAL areas and resilience to climate change |
| Challenges | Delayed county contribution and flooding of the borehole site. |
| Remarks | On-going project |
| Total Contract Sum (GoK + Foreign) | KES 60,838,709.27 |
|---|---|
| GoK Contract Sum | KES 5,550,830.00 |
| Foreign Contract Sum | KES 55,287,879.27 |
| Cumulative Expenditure | KES 31,878,815.36 |
| Outstanding Cost | KES 28,959,893.91 |
| Source | Type | Amount (KES) |
|---|---|---|
| Danida | Grant | 55,287,879.27 |
| Gok | Grant | 5,550,830.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 5,550,830.00 |
| 2022/23 | Approved | GOK | 55,287,879.27 |
| Target Households | 1,635 |
|---|---|
| Target Population | 8,175 |