Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Borehole |
| Agency | Water Sector Trust Fund |
| Program | Sustainable Management and Access to Water and Sanitation in the ASALs |
| Progress | 95.00% |
| County | Garissa |
|---|---|
| Constituency | Dadaab |
| Ward | Daadab & Fafi |
| Setting | Rural |
| Coordinates | 0.114998, 40.707736 |
| Start Date | 2022-07-12 |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | M/s Libinstar Enterprises Ltd. |
| Consultant | None |
| Target Areas | Daadab, Fafi |
| Scope of Works | Rehabilitation of 3 No. borehole and fencing, 3 No. 7.5 KW solar pumping system installation, 5.2 Kms HDPE pipeline extension, 1 No. Water Kiosks and 13 tapstands, 4 No. 4 door VIP latrines, CLTS triggering in 60 villages, 10-acre woodlot in Ifo and15 Arce on commercial pasture production |
| Impacts | increased access to water and sanitation services in ASAL areas and resilience to climate change |
| Challenges | Water project improvement works |
| Remarks | On-going project |
| Total Contract Sum (GoK + Foreign) | KES 82,711,673.25 |
|---|---|
| GoK Contract Sum | KES 7,658,626.25 |
| Foreign Contract Sum | KES 75,053,047.00 |
| Cumulative Expenditure | KES 55,859,912.94 |
| Outstanding Cost | KES 26,851,760.31 |
| Source | Type | Amount (KES) |
|---|---|---|
| Danida | Grant | 75,053,047.00 |
| Gok | Grant | 7,658,626.25 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 7,658,626.25 |
| 2022/23 | Approved | GOK | 75,053,047.00 |
| Target Households | 800 |
|---|---|
| Target Population | 4,800 |