Loima, Lokichoggio & Nanaam Water Project

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyWater Sector Trust Fund
ProgramSustainable Management and Access to Water and Sanitation in the ASALs (SWASAP)
Progress40.00%

Location Information

CountyTurkana
ConstituencyTurkana West
WardLokiriama-Lorengipi, Lobei, Lokichogio and Nanam Wards
SettingRural
Coordinates4.200000, 34.350000

Timeline & Impact

Start Date2022-07-12
Planned End DateN/A
Actual End DateN/A
ContractorShallowline investment Ltd
ConsultantNone
Target AreasLoima, Turkana west
Scope of WorksConstruct 30,000m3 water pan, Drill borehole, solar powered system, solar powered system, 12m high 50m3 steel tank, 3 No. water Kiosks, 2.5 Km 3" HDPE PN16 Rising mains, 3.5 Km 2" HDPE PN12 Distribution lines, 3no. Water Kiosks, 10m high 50m3 elevated steel tank, ยท2No. Cattle troughs, 2No. 4 door VIP latrines, CLTS in 75 Villages, 30,000m3 water pan, 2 No. 30m x8m shade nets
ImpactsThese activities will provide communities with reliable access to safe water, reducing water scarcity and improving overall well-being.
ChallengesInsecurity and poor road infrastrcture. Low capacty of the implementing partner.
RemarksOn-going project

Project Cost

Total Contract Sum (GoK + Foreign)KES 88,453,671.79
GoK Contract SumKES 8,615,042.67
Foreign Contract SumKES 79,838,629.12
Cumulative ExpenditureKES 52,138,894.06
Outstanding CostKES 36,314,777.73

Funding Sources

SourceTypeAmount (KES)
Danida Grant 36,739,402.14
Gok Grant 8,615,042.67

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 8,615,042.67
2022/23 Approved GOK 79,838,629.12

Beneficiaries

Target Households2,700
Target Population13,500