Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Borehole |
| Agency | Water Sector Trust Fund |
| Program | Sustainable Management and Access to Water and Sanitation in the ASALs (SWASAP) |
| Progress | 50.00% |
| County | Marsabit |
|---|---|
| Constituency | Laisamis |
| Ward | Laisamis |
| Setting | Rural |
| Coordinates | 2.593256, 37.081692 |
| Start Date | 2022-07-12 |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Samsung limited |
| Consultant | None |
| Target Areas | Olturot |
| Scope of Works | Rehabilitation of Olturot Water Supply, 4.0 km pipeline rehabilitation, rehabilitation of 4no Masonry tanks, 100m3 elevated steel tank, 2 NoWater Kiosk, 2 No Water troughs, rehabilitation of solar pumping systems and repair of fence. Springs intake works , CLTS 28 Villages, 2 no 3 door VIP latrine, 30,000m3 Water pan |
| Impacts | increased access to water and sanitation services in ASAL areas and resilience to climate change |
| Challenges | Political interference and low contrcator capacity. |
| Remarks | On-going project |
| Total Contract Sum (GoK + Foreign) | KES 49,535,078.36 |
|---|---|
| GoK Contract Sum | KES 2,198,741.44 |
| Foreign Contract Sum | KES 47,336,336.92 |
| Cumulative Expenditure | KES 44,949,418.20 |
| Outstanding Cost | KES 4,585,660.16 |
| Source | Type | Amount (KES) |
|---|---|---|
| Danida | Grant | 47,336,336.92 |
| Gok | Grant | 2,198,741.44 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 2,198,741.44 |
| 2022/23 | Approved | GOK | 47,336,336.92 |
| Target Households | 600 |
|---|---|
| Target Population | 3,000 |