Moyale Sub-county Integrated Project

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyWater Sector Trust Fund
ProgramSustainable Management and Access to Water and Sanitation in the ASALs (SWASAP)
Progress80.00%

Location Information

CountyMarsabit
ConstituencyMoyale
WardSololo, Golbo and Rawana
SettingRural
Coordinates3.151128, 39.250957

Timeline & Impact

Start Date2022-07-12
Planned End DateN/A
Actual End DateN/A
ContractorMs frontier Engenierring
ConsultantNone
Target Areassololo
Scope of WorksRepair of masonry tanks, rehabilitation of 2 No. Masonry and a 4.7 km pipeline extension, 2 No. 11KW solar system installation.2 No. Water Kiosk, 50m3 Elevated steel tank, 2 No. Water trough, CLTS in 30 Villages, 4 No 3 door VIP latrines, Desilting of a 30,000m3 water pan
Impactsincreased access to water and sanitation services in ASAL areas and resilience to climate change
Challengesconflict betwwen the Gold miners and community.
RemarksOn-going project

Project Cost

Total Contract Sum (GoK + Foreign)KES 41,614,399.82
GoK Contract SumKES 1,283,676.00
Foreign Contract SumKES 40,330,723.82
Cumulative ExpenditureKES 37,959,794.97
Outstanding CostKES 3,654,604.85

Funding Sources

SourceTypeAmount (KES)
Danida Grant 40,330,723.82
Gok Grant 1,283,676.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 1,283,676.00
2022/23 Approved GOK 40,330,723.82

Beneficiaries

Target Households1,300