Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Borehole |
| Agency | Water Sector Trust Fund |
| Program | Sustainable Management and Access to Water and Sanitation in the ASALs (SWASAP) |
| Progress | 70.00% |
| County | Tana River |
|---|---|
| Constituency | Galole |
| Ward | Kinakomba Ward, Wenje and Vukoni villages |
| Setting | Rural |
| Coordinates | 1.792889, 40.110416 |
| Start Date | 2022-07-12 |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | M/s Samsun Holdings |
| Consultant | None |
| Target Areas | Wenje, Vukoni |
| Scope of Works | Construct 30,000m3 Water pan, drill and develop 1 borehole, 5km pipeline extension, Rehabilitation of 6 Water kiosks, Installation of Solar system, 100m3 elevated steel tank |
| Impacts | increased access to water and sanitation services in ASAL areas and resilience to climate change |
| Challenges | Poor water quality realised after drilling. Low implementing partner capacity. |
| Remarks | On-going project |
| Total Contract Sum (GoK + Foreign) | KES 49,189,963.27 |
|---|---|
| GoK Contract Sum | KES 3,771,000.00 |
| Foreign Contract Sum | KES 45,418,963.27 |
| Cumulative Expenditure | KES 42,248,134.52 |
| Outstanding Cost | KES 6,941,828.75 |
| Source | Type | Amount (KES) |
|---|---|---|
| Danida | Grant | 45,418,963.27 |
| Gok | Grant | 3,771,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 3,771,000.00 |
| 2022/23 | Approved | GOK | 45,418,963.27 |
| Target Households | 960 |
|---|---|
| Target Population | 4,800 |