Wenje Kipendi Vukoni Water Supply

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyWater Sector Trust Fund
ProgramSustainable Management and Access to Water and Sanitation in the ASALs (SWASAP)
Progress70.00%

Location Information

CountyTana River
ConstituencyGalole
WardKinakomba Ward, Wenje and Vukoni villages
SettingRural
Coordinates1.792889, 40.110416

Timeline & Impact

Start Date2022-07-12
Planned End DateN/A
Actual End DateN/A
ContractorM/s Samsun Holdings
ConsultantNone
Target AreasWenje, Vukoni
Scope of WorksConstruct 30,000m3 Water pan, drill and develop 1 borehole, 5km pipeline extension, Rehabilitation of 6 Water kiosks, Installation of Solar system, 100m3 elevated steel tank
Impactsincreased access to water and sanitation services in ASAL areas and resilience to climate change
ChallengesPoor water quality realised after drilling. Low implementing partner capacity.
RemarksOn-going project

Project Cost

Total Contract Sum (GoK + Foreign)KES 49,189,963.27
GoK Contract SumKES 3,771,000.00
Foreign Contract SumKES 45,418,963.27
Cumulative ExpenditureKES 42,248,134.52
Outstanding CostKES 6,941,828.75

Funding Sources

SourceTypeAmount (KES)
Danida Grant 45,418,963.27
Gok Grant 3,771,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 3,771,000.00
2022/23 Approved GOK 45,418,963.27

Beneficiaries

Target Households960
Target Population4,800