Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Water Sector Trust Fund |
| Program | Green Growth and Employment Programme (GGEP) |
| Progress | 100.00% |
| County | Tana River |
|---|---|
| Constituency | Garsen |
| Ward | Tarasa |
| Setting | Rural |
| Coordinates | -2.432815, 40.203353 |
| Start Date | N/A |
|---|---|
| Planned End Date | 2020-01-12 |
| Actual End Date | N/A |
| Contractor | Tana Water and Sanitation Company |
| Consultant | None |
| Target Areas | Garsen |
| Scope of Works | Hydrogeological survey, EIA, design, 30M large diameter well, submersible pump & solar system, fencing around solar site, 48m3 steel tank on a tower, 6No. Water kiosks, 4km pipeline, 2 No. VIP latrines |
| Impacts | Servicing additional 2,800 residents in low income area |
| Challenges | N/A |
| Remarks | Project completed and operational |
| Total Contract Sum (GoK + Foreign) | KES 16,299,400.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 16,299,400.00 |
| Cumulative Expenditure | KES 16,299,400.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Danida | Grant | 16,299,400.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 16,299,400.00 |
| Target Households | 467 |
|---|---|
| Target Population | 2,335 |