Project Detail Report
| Status | Completed |
|---|---|
| Type | Djabia |
| Agency | Water Sector Trust Fund |
| Program | Green Growth and Employment Programme (GGEP) |
| Progress | 100.00% |
| County | Lamu |
|---|---|
| Constituency | Lamu East |
| Ward | Faza |
| Setting | Rural |
| Coordinates | -2.128750, 41.059833 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Lamu Water and Sewerage Company |
| Consultant | None |
| Target Areas | Shanga Rubu village |
| Scope of Works | Construction and fencing of 100m3 djabia at Shanga Rubu village, training community beneficiaries on beekeeping, procurement of 16 beehives & issuance to the beneficiaries and o develop Conservancy Development Management Plan (CDMP) |
| Impacts | Servicing additional 2,920 residents in Shanga Rubu village |
| Challenges | COVID and floods led to contract extension |
| Remarks | Project completed and operational |
| Total Contract Sum (GoK + Foreign) | KES 6,551,200.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 6,551,200.00 |
| Cumulative Expenditure | KES 13,102,400.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Danida | Grant | 6,551,200.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 6,551,200.00 |
| Target Households | 487 |
|---|---|
| Target Population | 2,435 |