Project Detail Report

Overview

StatusOngoing
TypePipeline
AgencyCentral Rift Valley Water Works Development Agency
ProgramGoK Directly Funded Projects for FY 2024/2044
Progress5.00%

Location Information

CountyTana River
ConstituencyGarsen
WardGarsen South
SettingRural
Coordinates0.077893, 36.456728

Timeline & Impact

Start Date2024-07-10
Planned End Date2025-01-01
Scope of WorksTrench excavation and pipelaying of 13km
ImpactsImproved access to water
ChallengesNot commenced