Huluqho Reverse Osmosis Project

Project Detail Report

Overview

StatusOngoing
TypeSanitation
AgencyWater Sector Trust Fund
ProgramGoK Priority Funding
Progress45.00%

Location Information

CountyGarissa
ConstituencyIjara
WardHuluqho
SettingRural
Coordinates1.147420, 41.051400

Timeline & Impact

Start Date2021-01-11
Planned End Date2022-01-12
Actual End Date2023-08-07
ContractorDrescoll Ltd
ConsultantNone
Target AreasHuluqho centre, Hulugho primary school, KDF & AP camp
Scope of WorksInstallation of 2 m3/hr Reverse Osmosis water treatment plant at Huluqho Girls Secondary School
ImpactsOnce completed the project will serve 9800 people
ChallengesProject has audit issues and stalled
RemarksAwaiting closure of audit by GAWASCO WSP issues to allow for final disbursement.

Project Cost

Total Contract Sum (GoK + Foreign)KES 13,200,000.00
GoK Contract SumKES 13,200,000.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 7,980,000.00
Outstanding CostKES 5,220,000.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 13,200,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved GOK 7,980,000.00

Beneficiaries

Target Households300
Target Population1,500