Sabasaba Water Pipelines Rehab. Project

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress100.00%

Location Information

CountyMurang'a
ConstituencyMaragua
WardKamahuha
SettingUrban
Coordinates-0.876771, 37.143055

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End Date2024-05-08
ContractorJohgab Construction Company Ltd
ConsultantNone
Target AreasSabasaba
Scope of Works• 7.685 km Pipeline Extension • 300 no. Cold Water Consumer Meters •Construction of 2 no. Water Kiosks
ImpactsThe project will enhance access to clean water for 2,215 people through a 7.685 km pipeline extension, 300 consumer meters for efficient water management, and two water kiosks to serve those without direct connections.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksProject completed and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,996,814.58
GoK Contract SumKES 3,199,490.33
Foreign Contract SumKES 16,797,324.25
Cumulative ExpenditureKES 18,134,437.50
Outstanding CostKES 1,862,377.08

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,199,490.33
Kfw Grant 16,797,324.25

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,797,324.25
2021/22 Approved GOK 3,199,490.33

Beneficiaries

Target Households443
Target Population2,215