Ogango-Kasule Water Supply Augmentation Project

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress100.00%

Location Information

CountyKisumu
ConstituencyKisumu East
WardKolwa Central Ward
SettingUrban
Coordinates-0.077958, 34.789670

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorFramoc Agencies Ltd
ConsultantNone
Target AreasOgango and Kasule
Scope of Works• Construction of 2 no. water kiosks, • 100no. Cold Water Consumer Meters • 3.810 Km Pipeline Extensions
ImpactsThe project will improve access to clean water for 12,226 people through a 3.810 km pipeline extension, 100 consumer meters for efficient water distribution, and two water kiosks to serve those without direct connections.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksProject completed and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,131,115.50
GoK Contract SumKES 3,060,978.48
Foreign Contract SumKES 16,070,137.02
Cumulative ExpenditureKES 19,130,823.69
Outstanding CostKES 291.81

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,060,978.48
Kfw Grant 16,070,137.02

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,070,137.02
2021/22 Approved GOK 3,060,978.48

Beneficiaries

Target Households2,445
Target Population12,226