Project Detail Report
| Status | Completed |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 100.00% |
| County | Embu |
|---|---|
| Constituency | Mbeere South |
| Ward | Mbeti South Ward |
| Setting | Urban |
| Coordinates | -0.710202, 37.517568 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | N/A |
| Contractor | Fahimyasin Company, Framoc Agencies Limited, Tredak Limited and Edema Contractors Limited |
| Consultant | None |
| Target Areas | Gachuriri |
| Scope of Works | • 14 km pipeline extension • Construction of 1 no. Closed kiosk • 200 no. Cold Water Consumer Meters • 1 no. 100 mm Master Meter |
| Impacts | The project will enhance water access for 5,695 people through a 14 km pipeline extension, 200 consumer meters for efficient distribution, a closed water kiosk for public access, and a 100 mm master meter for improved monitoring and management. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | Project completed and operational |
| Total Contract Sum (GoK + Foreign) | KES 17,723,307.00 |
|---|---|
| GoK Contract Sum | KES 2,835,729.12 |
| Foreign Contract Sum | KES 14,887,577.88 |
| Cumulative Expenditure | KES 15,903,408.04 |
| Outstanding Cost | KES 1,819,898.96 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 2,835,729.12 |
| Kfw | Grant | 14,887,577.88 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 14,887,577.88 |
| 2021/22 | Approved | GOK | 2,835,729.12 |
| Target Households | 1,139 |
|---|---|
| Target Population | 5,695 |