Augmenting Of Water Distribution Systems In Oljabet Town And Site Phase 2

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress100.00%

Location Information

CountyLaikipia
ConstituencyLaikipia West
WardGithiga
SettingUrban
Coordinates0.174559, 36.377708

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorJoynary Engineering Company Ltd, Greenways International Company Ltd and Danco Capital Ltd
ConsultantNone
Target AreasNyahururu Oljabet
Scope of Works• 17.14 km pipeline extension, • 300 no. Cold Water Consumer Meters
ImpactsThe project will improve water access for 9,000 people through a 17.14 km pipeline extension and 300 consumer meters, enhancing distribution efficiency and service reliability.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksProject completed and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,996,814.58
GoK Contract SumKES 3,199,490.33
Foreign Contract SumKES 16,797,324.25
Cumulative ExpenditureKES 19,034,534.88
Outstanding CostKES 962,279.70

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,199,490.33
Kfw Grant 16,797,324.25

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,797,324.25
2021/22 Approved GOK 3,199,490.33

Beneficiaries

Target Households1,800
Target Population9,000