Lower Aguthi Gaaki Water Supply Project

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress100.00%

Location Information

CountyNyeri
ConstituencyMathira
WardKaratina
SettingUrban
Coordinates-0.501805, 37.024581

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorSemcon Engineering
ConsultantNone
Target AreasKaratina
Scope of Works• 8km pipeline extension • 300no. 15mm Volumetric meters
ImpactsThe project will enhance water access for 9,687 people through an 8 km pipeline extension and 300 volumetric meters (15mm), ensuring efficient distribution and consumption monitoring.
ChallengesSlow release GOK funds, Slow pace of construction
Remarksnone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,882,800.00
GoK Contract SumKES 3,181,248.00
Foreign Contract SumKES 16,701,552.00
Cumulative ExpenditureKES 17,654,020.00
Outstanding CostKES 2,228,780.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,181,248.00
Kfw Grant 16,701,552.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,701,552.00
2021/22 Approved GOK 3,181,248.00

Beneficiaries

Target Households1,937
Target Population9,687