Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 96.00% |
| County | Mandera |
|---|---|
| Constituency | Mandera East |
| Ward | Rhamu |
| Setting | Urban |
| Coordinates | -0.501806, 37.024581 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | 2025-06-02 |
| Contractor | Tabarak Construction Limited |
| Consultant | None |
| Target Areas | Border Point 1 |
| Scope of Works | • 3.81km Pipeline extension • 100m3 Elevated steel tank • 4 no. Closed kiosks |
| Impacts | The project will enhance water access for 10,821 people through a 3.81 km pipeline extension, a 100m³ elevated steel tank for improved storage and supply, and four closed water kiosks to serve the community efficiently. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | none |
| Total Contract Sum (GoK + Foreign) | KES 17,658,910.50 |
|---|---|
| GoK Contract Sum | KES 2,825,425.68 |
| Foreign Contract Sum | KES 14,833,484.82 |
| Cumulative Expenditure | KES 17,569,755.95 |
| Outstanding Cost | KES 89,154.55 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 2,825,425.68 |
| Kfw | Grant | 14,833,484.82 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 14,833,484.82 |
| 2021/22 | Approved | GOK | 2,825,425.68 |
| Target Households | 2,164 |
|---|---|
| Target Population | 10,821 |