Mitunguu Water Project

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress100.00%

Location Information

CountyMeru
ConstituencyImenti South
WardMitunguu
SettingUrban
Coordinates-0.108876, 37.782755

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorNoor Consult
ConsultantNone
Target AreasMitunguu
Scope of Works• 14 km Pipeline extension • 9 no. Master meters
ImpactsThe project will enhance water access for 11,800 people through a 14 km pipeline extension and nine master meters, ensuring efficient water distribution and monitoring.
ChallengesSlow release GOK funds, Slow pace of construction
Remarksnone

Project Cost

Total Contract Sum (GoK + Foreign)KES 18,279,870.00
GoK Contract SumKES 2,924,779.20
Foreign Contract SumKES 15,355,090.80
Cumulative ExpenditureKES 18,150,476.01
Outstanding CostKES 129,393.99

Funding Sources

SourceTypeAmount (KES)
Gok Grant 2,924,779.20
Kfw Grant 15,355,090.80

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 15,355,090.80
2021/22 Approved GOK 2,924,779.20

Beneficiaries

Target Households2,360
Target Population11,800