Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 93.00% |
| County | Makueni |
|---|---|
| Constituency | Kibwezi East |
| Ward | Emali/Mulala |
| Setting | Urban |
| Coordinates | -2.524150, 38.030763 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | N/A |
| Contractor | Suwina Investment Ltd and Katulani Building and Construction Ltd |
| Consultant | None |
| Target Areas | Machinery Town |
| Scope of Works | • 250 no. Cold Water Consumer meters • 5,300m Pipeline Extension • Construction of 1 no. 150m3 Masonry Tank |
| Impacts | The project will improve water access for 4,753 people through a 5.3 km pipeline extension, 250 consumer meters for efficient distribution, and the construction of a 150m³ masonry tank to enhance storage capacity. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | none |
| Total Contract Sum (GoK + Foreign) | KES 16,660,707.00 |
|---|---|
| GoK Contract Sum | KES 2,665,713.12 |
| Foreign Contract Sum | KES 13,994,993.88 |
| Cumulative Expenditure | KES 16,252,687.38 |
| Outstanding Cost | KES 408,019.62 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 2,665,713.12 |
| Kfw | Grant | 13,994,993.88 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 13,994,993.88 |
| 2021/22 | Approved | GOK | 2,665,713.12 |
| Target Households | 951 |
|---|---|
| Target Population | 4,753 |