Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 70.00% |
| County | Migori |
|---|---|
| Constituency | Kuria West |
| Ward | Bukira East |
| Setting | Urban |
| Coordinates | -1.199186, 34.616116 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | N/A |
| Contractor | Lemura Engineering Limited |
| Consultant | None |
| Target Areas | Kehancha |
| Scope of Works | • 10,500m Pipeline extension • 1 Unit of water pump set • 500no. Consumer metres • 1no. 12m High 100m3 elevated steel tank • Fencing of tank area |
| Impacts | The project will enhance water access for 9,200 people through a 10.5 km pipeline extension, 500 consumer meters for efficient distribution, a 12m high 100m³ elevated steel tank for improved storage, a water pump set to boost supply, and fencing of the tank area for security. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | none |
| Total Contract Sum (GoK + Foreign) | KES 19,843,091.10 |
|---|---|
| GoK Contract Sum | KES 3,174,894.58 |
| Foreign Contract Sum | KES 16,668,196.52 |
| Cumulative Expenditure | KES 17,289,690.00 |
| Outstanding Cost | KES 2,553,401.10 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 3,174,894.58 |
| Kfw | Grant | 16,668,196.52 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 16,668,196.52 |
| 2021/22 | Approved | GOK | 3,174,894.58 |
| Target Households | 1,840 |
|---|---|
| Target Population | 9,200 |