Kehancha Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress70.00%

Location Information

CountyMigori
ConstituencyKuria West
WardBukira East
SettingUrban
Coordinates-1.199186, 34.616116

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorLemura Engineering Limited
ConsultantNone
Target AreasKehancha
Scope of Works• 10,500m Pipeline extension • 1 Unit of water pump set • 500no. Consumer metres • 1no. 12m High 100m3 elevated steel tank • Fencing of tank area
ImpactsThe project will enhance water access for 9,200 people through a 10.5 km pipeline extension, 500 consumer meters for efficient distribution, a 12m high 100m³ elevated steel tank for improved storage, a water pump set to boost supply, and fencing of the tank area for security.
ChallengesSlow release GOK funds, Slow pace of construction
Remarksnone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,843,091.10
GoK Contract SumKES 3,174,894.58
Foreign Contract SumKES 16,668,196.52
Cumulative ExpenditureKES 17,289,690.00
Outstanding CostKES 2,553,401.10

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,174,894.58
Kfw Grant 16,668,196.52

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,668,196.52
2021/22 Approved GOK 3,174,894.58

Beneficiaries

Target Households1,840
Target Population9,200