Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress
87.00%
Location Information
County
Kajiado
Constituency
Kajiado Central
Ward
Majengo
Setting
Urban
Coordinates
-1.827752, 36.790780
Timeline & Impact
Start Date
2022-06-04
Planned End Date
2023-06-04
Actual End Date
N/A
Contractor
Isginia Scandic Ltd
Consultant
None
Target Areas
Kajiado
Scope of Works
• 10 km Pipeline extension,
• Construction of 1no. Closed kiosks,
• 103 no. Cold Water Consumer meters
• Construction of 150m3 elevated steel tank,
• Solarization unit for 1no. Borehole
Impacts
The project will enhance water access for 12,000 people through 103 consumer meters for efficient distribution.