Saina Majengo Water Project

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress87.00%

Location Information

CountyKajiado
ConstituencyKajiado Central
WardMajengo
SettingUrban
Coordinates-1.827752, 36.790780

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorIsginia Scandic Ltd
ConsultantNone
Target AreasKajiado
Scope of Works• 10 km Pipeline extension, • Construction of 1no. Closed kiosks, • 103 no. Cold Water Consumer meters • Construction of 150m3 elevated steel tank, • Solarization unit for 1no. Borehole
ImpactsThe project will enhance water access for 12,000 people through 103 consumer meters for efficient distribution.
ChallengesSlow release GOK funds, Slow pace of construction
Remarksnone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,769,127.00
GoK Contract SumKES 3,163,060.32
Foreign Contract SumKES 16,606,066.68
Cumulative ExpenditureKES 18,451,239.01
Outstanding CostKES 1,317,887.99

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,163,060.32
Kfw Grant 16,606,066.68

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,606,066.68
2021/22 Approved GOK 3,163,060.32

Beneficiaries

Target Households2,400
Target Population12,000