Overview
| Status | Ongoing |
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 65.00% |
Location Information
| County | Machakos |
| Constituency | Kangundo |
| Ward | Kangundo Central |
| Setting | Urban |
| Coordinates | -1.302820, 37.344869 |
Timeline & Impact
| Start Date | 2022-06-04 |
| Planned End Date | 2023-06-04 |
| Actual End Date | 2023-06-11 |
| Contractor | Ecoworld Construction Limited & Alpha Sight General Supplies Limited |
| Consultant | None |
| Target Areas | Kangundo |
| Scope of Works | • Construction of 2no.closed kiosks
• Metering 200no.
• Pipeline extension 10.8km
• Renovation of pump house and storage tank |
| Impacts | The project will enhance water access for 10,750 people through 200 metered connections for efficient distribution. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | none |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 16,071,560.40 |
| GoK Contract Sum | KES 2,571,449.66 |
| Foreign Contract Sum | KES 13,500,110.74 |
| Cumulative Expenditure | KES 6,092,259.17 |
| Outstanding Cost | KES 9,979,301.23 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
2,571,449.66 |
| Kfw |
Grant |
13,500,110.74 |
Budget Allocations by Fiscal Year
| Fiscal Year | Stage | Funding Side | Amount (KES) |
| 2021/22 |
Approved |
FOREIGN |
13,500,110.74 |
| 2021/22 |
Approved |
GOK |
2,571,449.66 |
Beneficiaries
| Target Households | 2,150 |
| Target Population | 10,750 |