Kihumbu-Ini Water Project

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress100.00%

Location Information

CountyMurang'a
ConstituencyGatanga
WardKihumbu-Ini
SettingUrban
Coordinates-0.930101, 36.981532

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End Date2024-06-10
ContractorJoghab Construction Company
ConsultantNone
Target AreasMabanda
Scope of Works• 6.4 km pipeline extension • 1000no. Cold Water Consumer Meters
ImpactsThe project will enhance water access for 8,292 people through a 6.4 km pipeline extension and 1,000 cold water consumer meters, ensuring efficient distribution and improved service delivery.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksProject completed and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 17,798,209.80
GoK Contract SumKES 2,847,713.57
Foreign Contract SumKES 14,950,496.23
Cumulative ExpenditureKES 17,772,650.00
Outstanding CostKES 25,559.80

Funding Sources

SourceTypeAmount (KES)
Gok Grant 2,847,713.57
Kfw Grant 14,950,496.23

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 14,950,496.23
2021/22 Approved GOK 2,847,713.57

Beneficiaries

Target Households1,658
Target Population8,292