Project Detail Report
| Status | Completed |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 100.00% |
| County | Murang'a |
|---|---|
| Constituency | Gatanga |
| Ward | Kihumbu-Ini |
| Setting | Urban |
| Coordinates | -0.930101, 36.981532 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | 2024-06-10 |
| Contractor | Joghab Construction Company |
| Consultant | None |
| Target Areas | Mabanda |
| Scope of Works | • 6.4 km pipeline extension • 1000no. Cold Water Consumer Meters |
| Impacts | The project will enhance water access for 8,292 people through a 6.4 km pipeline extension and 1,000 cold water consumer meters, ensuring efficient distribution and improved service delivery. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | Project completed and operational |
| Total Contract Sum (GoK + Foreign) | KES 17,798,209.80 |
|---|---|
| GoK Contract Sum | KES 2,847,713.57 |
| Foreign Contract Sum | KES 14,950,496.23 |
| Cumulative Expenditure | KES 17,772,650.00 |
| Outstanding Cost | KES 25,559.80 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 2,847,713.57 |
| Kfw | Grant | 14,950,496.23 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 14,950,496.23 |
| 2021/22 | Approved | GOK | 2,847,713.57 |
| Target Households | 1,658 |
|---|---|
| Target Population | 8,292 |